SOW - Template - Example
Below is a realistic sample Statement of Work (SOW)
for an Azure Cloud Migration Project that a Cloud Architect, Solution
Architect, Delivery Manager, or Director might prepare for a customer.
STATEMENT OF WORK (SOW)
Project Name
Azure Cloud Migration & Infrastructure Modernization
Program
Customer: ABC Manufacturing Ltd.
Service Provider: XYZ Cloud Consulting Services
Version: 1.0
Date: June 2026
1.
Project Overview
ABC Manufacturing Ltd. intends to migrate its on-premises
infrastructure to Microsoft Azure to improve scalability, security, operational
efficiency, and disaster recovery capabilities.
XYZ Cloud Consulting Services will design, build, and
migrate the required infrastructure and workloads into Azure following
Microsoft Cloud Adoption Framework (CAF) best practices.
2.
Objectives
The objectives of this engagement are:
- Migrate
existing workloads to Azure.
- Establish
an Azure Landing Zone.
- Implement
secure networking architecture.
- Improve
business continuity and disaster recovery.
- Enable
centralized monitoring and governance.
- Reduce
operational overhead associated with on-premises infrastructure.
- Establish
scalable cloud infrastructure for future growth.
3. Scope
of Work
The Service Provider will perform the following activities:
Assessment & Discovery
- Infrastructure
assessment
- Dependency
analysis
- Application
inventory
- Network
assessment
Azure Foundation Setup
- Azure
Tenant onboarding
- Management
Groups
- Subscription
structure
- Resource
Groups
- Azure
Policies
- RBAC
implementation
Networking
- Virtual
Networks
- Subnets
- Network
Security Groups
- VPN
Gateway configuration
- Private
DNS configuration
Compute Migration
- Migration
of 25 Windows Servers
- Migration
of 10 Linux Servers
- Azure
Virtual Machine deployment
- VM
sizing and optimization
Monitoring & Operations
- Azure
Monitor
- Log
Analytics Workspace
- Alerts
configuration
- Dashboard
creation
Backup & Recovery
- Azure
Backup
- Recovery
Services Vault
- Backup
policies
- Disaster
recovery planning
4. Out of
Scope
The following items are excluded from this engagement:
- Application
code modification
- Application
redesign or modernization
- Database
schema redesign
- Third-party
software licensing
- End-user
training
- ERP
customization
- SAP
migration
- Non-Azure
cloud environments
Any out-of-scope work will require a separate Change Request
(CR).
5.
Deliverables
The Service Provider shall deliver:
|
Deliverable |
Description |
|
Discovery
Report |
Assessment
findings and recommendations |
|
Azure
Landing Zone |
Enterprise-ready
Azure foundation |
|
Network
Architecture Document |
Detailed
network design |
|
Migration
Runbook |
Step-by-step
migration plan |
|
Monitoring
Dashboard |
Azure
operational dashboards |
|
Backup
Configuration |
Backup
policies and implementation |
|
As-Built
Documentation |
Final
environment documentation |
|
Knowledge
Transfer Session |
Handover
to operations team |
6.
Milestones
|
Milestone |
Duration |
|
Project
Kickoff |
Week 1 |
|
Discovery
Assessment |
Week
1-2 |
|
Landing
Zone Deployment |
Week 3 |
|
Network
Setup |
Week 4 |
|
Server
Migration |
Week
5-7 |
|
Monitoring
& Backup |
Week 8 |
|
User
Acceptance Testing |
Week 9 |
|
Production
Go-Live |
Week 10 |
|
Project
Closure |
Week 11 |
7.
Assumptions
The following assumptions apply:
- Customer
will provide required Azure subscriptions.
- Customer
will provide necessary access permissions.
- Customer
SMEs will be available during workshops.
- Network
connectivity between sites is operational.
- Required
firewall ports will be opened by the customer.
- Existing
infrastructure documentation is accurate.
- No
major application changes will occur during migration.
8. Risks
|
Risk |
Impact |
Mitigation |
|
Incomplete
infrastructure inventory |
High |
Discovery
validation workshops |
|
Network
latency issues |
Medium |
Performance
testing |
|
Resource
availability delays |
Medium |
Escalation
process |
|
Security
compliance issues |
High |
Security
review checkpoints |
|
Migration
downtime |
Medium |
Planned
maintenance windows |
9. Roles
& Responsibilities
Customer Responsibilities
- Provide
infrastructure access.
- Provide
project stakeholders.
- Participate
in workshops.
- Approve
deliverables.
- Perform
user acceptance testing.
Service Provider Responsibilities
- Design
Azure architecture.
- Execute
migration activities.
- Configure
monitoring and backup.
- Produce
project documentation.
- Conduct
knowledge transfer sessions.
10.
Acceptance Criteria
The project will be considered accepted when:
- All
in-scope servers are successfully migrated.
- Azure
Landing Zone is operational.
- Monitoring
dashboards are functioning.
- Backup
jobs complete successfully.
- Customer
completes User Acceptance Testing (UAT).
- All
agreed deliverables are submitted.
- Formal
sign-off is received from customer stakeholders.
12.
Commercial References
Engagement Model
Fixed Price Professional Services
Estimated Project Cost
|
Item |
Cost |
|
Assessment
Phase |
$15,000 |
|
Azure
Foundation Setup |
$20,000 |
|
Migration
Services |
$45,000 |
|
Monitoring
& Backup |
$10,000 |
|
Documentation
& KT |
$5,000 |
|
Total
Project Value |
$95,000 |
Payment
Terms
- 30%
upon project kickoff
- 40%
after migration completion
- 30%
upon final acceptance
Sign-Off
Customer Approval
Name: _______________________
Title: _______________________
Signature: ___________________
Date: _______________________
Service
Provider Approval
Name: _______________________
Title: _______________________
Signature: ___________________
Date: _______________________
This is very close to the format used by large consulting
firms such as Accenture, Infosys, TCS, Wipro, Cognizant, Capgemini, HCL, and
IBM for cloud migration and infrastructure transformation engagements.
Statement of Work (SOW)
Azure Cloud Migration & Infrastructure Modernization Program
Customer: ABC Manufacturing Ltd.
Service Provider: XYZ Cloud Consulting Services
Version: 1.0
Date: June 2026
Project Summary
Objective
Migrate infrastructure to Azure and modernize operations.
Duration
11 Weeks
Project Value
$95,000
Delivery Model
Fixed Price Professional Services
Statement of Work Details
1. Project Overview
ABC Manufacturing Ltd. intends to migrate its on-premises infrastructure to Microsoft Azure to improve scalability, security, operational efficiency, and disaster recovery capabilities.
2. Objectives
- Migrate workloads to Azure
- Establish Azure Landing Zone
- Implement secure networking
- Improve business continuity
- Enable centralized monitoring
- Reduce operational overhead
- Support future growth
Scope Definition
In Scope
- Infrastructure Assessment
- Application Inventory
- Azure Landing Zone
- Management Groups
- Subscriptions
- Resource Groups
- Azure Policies
- RBAC
- Virtual Networks
- Subnets
- NSGs
- VPN Gateway
- Private DNS
- 25 Windows Servers Migration
- 10 Linux Servers Migration
- Azure Monitor
- Log Analytics
- Backup & DR
Out of Scope
- Application Code Modification
- Application Redesign
- Database Schema Redesign
- Third-Party Licensing
- End User Training
- ERP Customization
- SAP Migration
- Non-Azure Cloud Platforms
Deliverables
| Deliverable | Description |
|---|---|
| Discovery Report | Assessment findings and recommendations |
| Azure Landing Zone | Enterprise-ready Azure foundation |
| Network Architecture Document | Detailed network design |
| Migration Runbook | Migration procedures |
| Monitoring Dashboard | Operational visibility |
| Backup Configuration | Backup implementation |
| As-Built Documentation | Final environment documentation |
| Knowledge Transfer Session | Operations handover |
Milestones
Risk Register
| Risk | Impact | Mitigation |
|---|---|---|
| Incomplete Infrastructure Inventory | High | Discovery Validation Workshops |
| Network Latency | Medium | Performance Testing |
| Security Compliance Issues | High | Security Reviews |
Service Level Agreements
99.9%
Infrastructure Availability
30 Min
Critical Incident Response
98%
Backup Success Rate
Commercial References
Total Project Value: $95,000
- Assessment Phase – $15,000
- Azure Foundation Setup – $20,000
- Migration Services – $45,000
- Monitoring & Backup – $10,000
- Documentation & KT – $5,000
Payment Terms
- 30% Project Kickoff
- 40% After Migration Completion
- 30% Final Acceptance
Comments